7,000+ customers without power.

Utility damage assessments continue along with significant clearing activities along Oppert Road and in the Garden District area. Six electric crews have worked diligently with four mutual aid crews from Riviera, Opelika, Sheffield, and Cullman. Additional support providing essential tree cutting include efforts include the Public Works Street Department, Dothan Utilities Water and Sewer crews, and Dothan Utilities contract tree cutting crews (Asplundh).

DU ELECTRIC CREW EFFORTS

Restored Cloverdale area

Continued work in 08-25 area including Kent, Newton, Burdeshaw and Porters (area)

Restored TV Road area

Continued work in 04-22 area including bridge at 3rd Ave. and Haven Dr. including Oppert Rd.

Restored Shady Brook area

Restored Flynn Substation area including Westgate to 431 and North on 431

Restored 01-23 area including Young America

Continued work in 11-21 area including Westgate and Denton; and 11-25 area including Griffin Dr.

Continued work in E. Wilson area

Restored Bruner Rd. area

Restored Bob Hall, Nottingham, Twin Lakes areas

Continued work in Stonebridge area

Restored 03-23 (partial) area including downtown and will continue working with additional outages

Continued work in Denton area inside RCC

PUBLIC WORKS, DU CREWS AND ASPLUNDH (TREE-CUTTING EFFORTS)

Oppert Rd.

08-25 inside RCC-all crews

Garden District area

Miscellaneous tree areas

NEXT MAJOR WORK AREAS

08-23-NW inside RCC, SW inside RCC, W. Main inside RCC

08-27-NW outside RCC, Kent Dr., Pettus St.
Service trucks continue to work on customer transformers, service taps, and service cuts in smaller, individual areas in efforts to restore service.